The first pour marks Redwing’s return to commercial production and establishes a second producing operation alongside How Mine, advancing Namib’s strategy to build a diversified, multi-asset gold production platform. The first gold pour follows an accelerated restart programme involving the rehabili...
11-23 21:43
Namib Minerals successfully poured first gold at Redwing Mine, Zimbabwe, achieving its November 2026 target. This marks Redwing's return to commercial production, complementing How Mine and advancing Namib's strategy to become a multi-asset gold producer. The milestone follows an accelerated restart program, with plans to increase production capacity through a higher-capacity winder by Q1 2027. CEO Tulani Sikwila highlighted this as a significant...
11-23 13:38
Namib Minerals has announced the successful commissioning of its Expanded Mill at How Mine, achieving a 94.6% availability factor. In October 2026, the mine processed 52,376 tonnes of ore, a 27% increase from the third-quarter monthly average, with gold production rising 21% to 2,396 ounces. Despite a lower head grade, metallurgical recovery improved to 86.7%. C1 cash costs decreased to US$1,155 per ounce, and AISC to US$1,783 per ounce, with fur...
11-16 13:30
Namib Minerals ("Namib" or the "Company") (NASDAQ:NAMM) today announced plans for an accelerated restart of operations at Redwing Mine in Zimbabwe, with first gold production expected in November 2026. The accelerated development programme builds on the completion of dewatering, refurbishment of cri...
11-04 07:41
Namib Minerals plans to restart operations at Zimbabwe's Redwing Mine ahead of schedule, targeting first gold production in November 2026. The accelerated restart follows the Zimbabwe Ministry of Mines' policy requiring foreign-owned operators to meet production thresholds by January 2027. Namib has refurbished mine infrastructure and resumed key activities, enabling an earlier return to production. The company aims to ramp up to 10,000 tonnes of...
11-03 23:36
Ramp-up completed well ahead of the six-to-eight-week timeline and the end-of-December target NEW YORK, Oct. 26, 2026 (GLOBE NEWSWIRE) -- Namib Minerals ("Namib" or "the Company") (NASDAQ:NAMM), today announced that the expanded milling plant at How Mine has been commissioned and is now operating at...
10-26 21:02
Namib Minerals announced that the expanded milling plant at How Mine is now operating at full capacity of 55,000 tonnes per month, exceeding the expected timeline by reaching full rate ahead of schedule. The expansion increased processing capacity by 36%, addressing milling constraints and enabling cost spreading across higher production volumes. The company expects to provide 2027 production and cost guidance in Q1 2027.
10-26 13:00
Namib Minerals completed the commissioning of its expanded milling plant at How Mine ahead of schedule, increasing monthly processing capacity from 40,500 to 55,000 tonnes, a 36% increase. The company aims to reach full capacity by December 2026 and restart Redwing Mine by January 2027. Namib Minerals is a gold producer operating in Zimbabwe, focusing on expanding its operations and restarting mines.
10-08 21:15
Namib Minerals (($NAMM)) has held its Q2 earnings call. Read on for the main hi...
10-02 08:09
Namib Minerals (NAMM) announced that its wholly owned subsidiary, Bulawayo Mining Company (Private) Limited, has secured a non-dilutive $6.5M new term loan facility from African Banking Corporation of...
09-30 15:26