2025 full-year guidance |
Prior | Current | Comments | ||
Production | MMboe | 186 - 196 | 188 - 195 | Includes the Greater Angostura assets divestment. |
Gas hub exposure15 | % of produced LNG | 28 - 35 | No change | |
Unit production cost | $/boe | 8.5 - 9.2 | 8.0 - 8.5 | Strong production and cost performance in H1 2025. |
Property, plant and equipment depreciation and amortisation | $ million | 4,500 - 5,000 | 4,700 - 5,000 | |
Exploration expense | $ million | 200 | No change | |
Payments for restoration | $ million | 700 - 1,000 | No change | |
Capital expenditure16 | $ million | 4,500 - 5,000 | 4,000 - 4,500 | Beaumont New Ammonia Project completion payment is expected in 2026, first ammonia production is planned for late 2025. |