热门资讯> 正文
2025-07-23 13:56
| 2025 full-year guidance |
| Prior | Current | Comments | ||
| Production | MMboe | 186 - 196 | 188 - 195 | Includes the Greater Angostura assets divestment. |
| Gas hub exposure15 | % of produced LNG | 28 - 35 | No change | |
| Unit production cost | $/boe | 8.5 - 9.2 | 8.0 - 8.5 | Strong production and cost performance in H1 2025. |
| Property, plant and equipment depreciation and amortisation | $ million | 4,500 - 5,000 | 4,700 - 5,000 | |
| Exploration expense | $ million | 200 | No change | |
| Payments for restoration | $ million | 700 - 1,000 | No change | |
| Capital expenditure16 | $ million | 4,500 - 5,000 | 4,000 - 4,500 | Beaumont New Ammonia Project completion payment is expected in 2026, first ammonia production is planned for late 2025. |